The conversion of Corfe Castle CE VC First School into a Primary School.

Project photographs

A selection of completion and construction photographs together with concept images for the project at Corfe Castle Primary School. (opens in a new window)

 

The project and background

The project at Corfe Castle Primary School (opens in a new window) was part of the reorganisation of Purbeck schools, which involved changing the educational structure from a three tier to a two tier system.

As part of this reorganisation, Corfe Castle CE First School became a 0.5 form entry primary school. The project involved the creation of a new hall including a servery and new entrance. The existing school was refurbished and remodelled to create a new classbase and resource area from the existing hall area.  The project started on site in December 2012 and was completed in September 2013.

The new school hall at Corfe Castle CE VC Primary School has been awarded Society for Construction and Architecture in Local Authorities (SCALA) (opens in a new window) CIVIC BUILDING of the YEAR 2014, in the small project category.

The design

The new hall area is 140 metres squared excluding the store, servery, WCs and boiler room. The materials were selected from studying the architecture of the existing school and nearby surroundings. The feature front elevation was constructed from Purbeck stone with brick to the side and rear elevations. The roof is plain clay tiles to match the existing with high level glazing providing a modern level of detailing.

The design and sustainability

Sustainable design solutions included the provision of photovoltaic panels, lighting controls and thermostats, energy efficient light fittings and energy efficient boilers.

External works and landscape

External works included the provision of a new fence parallel to the old stone wall, creating a secure boundary for the school, allowing pedestrian access from East Street to the new entrance porch.  A new 33 metre x 25 metre games court with a tarmac surface, surrounded by a fence and hedge was also provided.

The design team and main constructor

The project to convert Corfe Castle CE VC First School into a Primary School was procured and project managed by Dorset County Council's Dorset Property. The design team and main constructor were as follows:

Client: The Asset Management Group for Cabinet, represented by the Director of Children's Services

Project manager: Dorset County Council's Dorset Property

Architect: Dorset County Council's Dorset Property

Cost consultant: Dorset County Council's Dorset Property

Mechanical engineer: Dorset County Council's Dorset Property

Electrical engineer: Dorset County Council's Dorset Property

Landscape architect: Dorset County Council's Dorset Property

Structural engineer: Parsons Brinkerhoff Ltd

CDM co-ordinator: Stride Treglown

Clerk of works: Dorset County Council's Dorset Property

Main constructor: Interserve