Sherborne Abbey Primary School

The construction of new accommodation in an extension to the school and modification work to the existing building and external areas. 

The project and background 

Sherborne Abbey CE Primary School is located on the western edge of Sherborne.  The existing 1.5 form entry (FE) school was constructed in 1999 but due to an increase in the population of the school aged children in the area, the school needs to expand in size from 1.5FE (315 pupils) to 2FE (420 pupils).

To meet this need a new single storey extension to the western elevation of the existing school is being constructed.  The new accommodation will comprise of three new classbases, food technology room, two group rooms, toilets and associated ancillary spaces, landscape and drainage works. The existing Reception Area is also being extended and internally remodelled to provide adequate space.

To enable the construction works to progress whilst the school remains operational, temporary modular accommodation was installed in April 2017. It is planned that this will remain on site for 12 months during the course of the works.

Construction works commenced on site on Monday 3 July 2017.  The project will be completed in two sections with the Reception Area extension and remodelling being handed over to the school in January 2018 and the extension to the western elevation in March 2018.

The design

The design of the new extension follows the style and rhythm of the existing traditionally constructed school, being a masonry walling envelope under a pitched tiled roof covering. This will retain the established strong sense of identity and consistency. Where possible matching traditional materials will be used for the external envelope elements incorporating many repeat key features; in particular gable ends combining projecting buttresses complete with corbelled brickwork.

The landscape works will include the provision of new footpaths to link all new external door entrances to existing paths, hard and soft play areas providing fully accessible circulation routes for disabled users.

The new extensions will comply with current 2013 Part L Building Regulations following good energy design. Natural ventilation and daylight strategies will be employed with appropriate energy efficient equipment and controls installed. The current site security and access arrangements will remain in place and will be adopted in the new extensions.

The design team

The project to provide additional accommodation at Sherborne Abbey CE Primary School is being procured, project managed and designed by Dorset County Council's Dorset Property.  The design team and main constructor are as follows:

  • Client: The Managing our Assets Group, represented by the Corporate Director Children, Adults and Communities
  • Project manager: Dorset Property
  • Architect: Dorset Property
  • Cost consultant: Dorset Property
  • Mechanical engineer: Dorset Property
  • Electrical engineer: Dorset Property
  • Landscape architect: Dorset Property
  • Structural engineer: Dorset Property
  • Principal designer under CDM: Dorset Property
  • Clerk of works: Dorset Property
  • Main constructor: Morgan Sindall Construction & Infrastructure
  • Modular Accommodation Provider: McAvoy

 

Rate this page

Have some feedback?

Your feedback

This form is for reporting incorrect website content, technical issues, or general website feedback.

Contact us if you want to get in touch about a council service instead.

All fields are required.

Leave your email address so that we can provide a response.

This helps us direct your feedback to the appropriate council.